The current status shows that your boat is progressing well in the Detailing & QA stage.
At this point, targa and coachroof have been assembled and glassed. Gelcoat repairs of targa have been completed 80%.
The boat has recently been equipped with some critical parts to get closer to completion such as side hull windows, deck upper windows, front opening hatches, wiring and installation for the main power system ( Lithium batteries, DC/DC chargers, MPPTs, Charger/Inverter, Czone etc). Also, the bowspirit infrastructure has been completed and tested for bowspirit fitting. Frames for ceiling liner-upholstery installation have been manufactured and glassed.
Currently, the team is working on deck gear installations, all stanchions, deck fillers, windlass, exterior gelcoat works (70% done), fuel system plumbing, black water system plumbing, and preparation for timberworks. The upholstery kit production is due to start in week 20.