Production Update – Detailing & QA

Your boat has entered the Detailing and QA stage.

At this point, we have finished with all windows installations, antifouling, deck gear, BBQ, helm windows, all interior floorings, and all plumbing.

Currently, we are working on Lewmar deck hatches, electric systems (75%), shower glass, timber fitout, and freezer benchtop.

However, due to the global supply chain issue, we have quite a few missing parts that either pending for delivery date from the supplier or arrived later than we planned. We currently reschedule the completion date for your hull on the third week of March but we will keep you updated if there are any changes to this schedule.