The current status shows that your boat is progressing well in the Detailing & QA stage.
The boat has recently been equipped with some critical parts to get closer to completion. In which, the interior and exterior gelcoat repair and finishing works have reached a substantial 80% completion, significantly enhancing the boat’s aesthetic appeal. The black gelcoat on the deck has been completed. Hull and deck glass installations are currently in progress, and are anticipated to be finalized by the end of Week 36.
Concurrent with these efforts, preparations for plumbing and thru-hull fitting installations have commenced, ensuring a smooth and efficient process.