It is exciting that you boat now is in the Details & QA stage.
We recently completed the antifouling, all plumbing, flexiteek, nav station, galley, interior flooring, aircon, and all deck gear.
Currently remaining works are electric works (90% done) and aft bathroom vanity area. Our Production Team is also doing the checking around the boat to make sure that everything is good before shipping.