A new stage has just opened, and your boat is progressing well with some new parts completed recently.
At this point, we have completed some components comprised of dagger-board casings, chainplates, trampolines, carpet works, laminex bulkheads, all Lewmar hatches, and composite deck hatches.
Currently, we’re working on antifoul preparation, gunwale, daggerboard casing glassing, and companionway window liners. Besides, the electrical works have been started.