Your boat has already entered the new stage after assembly – Fitting out.
At this point, we have installed the rudders, forward beam, companionway flooring, Laminex bulkheads, galley bench top, carpet works, window liner, and the composite deck has been hatched.
We’re working on antifoul preparation, plumbing (50%), steering, Lewmar hatch, and deck gear (25%).