Production Update – Fit out

Your boat is progressing well in the second phase of Fit out stage.

We recently have installed engines, windlass, fwd beam, helm windows, steering, solar panels, trampoline, fwd beam. Plumbing stage-1 was also completed,
Our production team is working on deck gear (50% done), electric installations (50%), hull windows, and plumbing (75%). Timber fitout has started.