Your boat is progressing well in the last phase of Fit out stage.
We recently have finished all plumbing, galley bench top, trampolines, helm stations, solar panels, and antifouling.
Our production team is currently working on electric work phase 2 (90% done), timber fitout (90%), aircon, companionway flooring, water maker installation, and detailing tasks.