It is exciting that your boat has been moved to the Fit out stage.
We have recently done forward beam installation, trampoline, engines, hull windows, washing machine, aircon, and Laminex bulkheads.
Our production team is currently working on antifouling preparation, electric work (35% done), plumbing (75%), deck gear (75%), and rudder installation.