Production Update – Fit out 2

Your boat doing well moving forward to the second phase of fitting out.

We’re done with detailing the hull, midship, and starboard forward head. Painting jobs, plumbing, daggerboard, steering system, and starboard aft cabin are 70 – 80% completed. We are halfway towards the deck fitting out and glass window on deck installation.

We’ve also started to work on the saloon galley and anchor system. Currently, we are working on tank testing, fitting longeron and crossbeam, and mast painting.