Production Update – Fit out 2

Your boat is now at the second phase of fitting out

At this point, we have done with antifoul preparation, all deck gear, helm windows, and forward bunk liners. All interior flooring has also been completed.

Currently, we are completing the remaining window glass installations, electric work is 75% done. 80% of plumbing jobs and timber outfitting have also been carried out.