Production Update – Fit out

It is exciting that your boat is progressing well in the Fit out stage.

We have recently had engines installed, fwd opening windows installed, Laminex bulkheads, fwd beam and A-frame installed, Lewmar deck hatches, deck gear completed, all windows completed.

Our Production team is working on timber fitout (20% done), ceiling and wall liners, electric work (50%), and plumbing (30%).