Your boat is progressing well in the Fit out stage.

We recently completed the deck hardware, stanchion, windows & hatches, A-frame, trampoline & anchor box.

Our Production team is currently working on steering (85%), electric (80%), plumbing & LPG (85%), timber fitout (80%) and solar panels 80%.