It is exciting that your boat has been moved and progressing well in the Fit out stage.
We recently completed the installation of engines, saloon windows, hullside windows, and A-frame. Gelcoat repair is also finished.
Our Production team is currently working on deck hardware, hatches, plumbing, and LPG. Electric system is about 70% of completion.