Production Update – Fit out

Your boat has already entered the new stage after assembly – fitting out.

At this point, we have had the rudder installed, deck gear, composite deck hatches, companionway flooring, helm windows, window liners, forward-opening windows, and solar panels installed.

The ongoing tasks these days include A-frame installation, plumbing (50% done), forward bunk headliners, exhaust system, and antifoul preparation.