Your boat has been moved to the new stage after assembly – fitting out.
Most of the work on the boat had been completed including rudders installation, solar panels, composite deck hatches, window liners, carpet works, heating system, and companionway flooring.
At this point, we are working on the trampoline flange, cockpit drains, deck gear, bunk headliners, and plumbing (50%). However, due to the global supply chain issue, we have quite a few missing parts that either pending for delivery date from supplier or arrived later that we planned. We currently reschedule the completion date for your boat on the third week of April but we will keep you updated if there are any changes to this schedule.