Your boat is progressing well in the first phase of fitting out.
At this point, we have done with the hardtop installation, trampoline flange, window liners, antifoul preparation, and battery cables. In addition, the engines were also installed.
Now, we are working on deck gear, interior composite parts and plumbing. All windows will be installed by 10th of March as per our plan.