You boat is progressing well in the Fit out stage.
We have done the tasks of deck non-skid, mast base, deck hatches, solar panels, interior headliners preparation, and galley furniture. The companionway flooring, heating system, deck gear, composite deck hatches, trampoline and BBQ have also been completed.
Our production team is currently working on the steering system, the aircon, timber fitout (50%), electric system (50%), starboard aft bunk, and cabin healiners. Last late parts are estimated to arrive until last week of September and first week of October for installation.