Your boat has been progressing well in the Fit out stage.
We have done the jobs of dinghy davits, daggerboard completion, mast base completion, escape hatches, anchor/windlass assembly, plumbing works, forward beam, hardtop installation, deck gear installation, aircon installation base, wall and headliners.
Our Production Team is working on steering system, deck gear (50%), solar panels, electric installations (40%), timber fitout (30%).