Production Update – Fitout 2

We have completed the work with antifoul preparation, anchor system, sado glass on hardtop, helm seats, deck gear, all composite hatches, floors, and fwd opening windows. Daggerboards casings are also installed.
Currently, we are working on window liners midship, and galley benchtops. We are 50% done with plumbing, 75% done with electricity and started detailing works.