Production Update – Fitout 2

Jobs have been completed on deck gear, hardtop nonskid repair, trifold door, engines, Sado glass, and floors. Electric system is 75% done; interior timber, steps, plumbing have been progressed to 50% of completion. Boat is well on schedule.