Production update – Fit out 2

Your boat is doing well in the final days of fit out 2.

Exterior: We have done with longeron and fwd beam. Cockpit roof is also completed. We are 90% done with deck gear installation, anchor system, helm area, and steering.

Interior: We are done with flooring, navigation station and plumbing. Currently, we are focusing on galley, settee, cabins and saloon area.

Engineering: We are testing the engine and equipment on the boat.