Your boat is progressing well in the second phase of fitting out.

The mast, boom, and forward beam have been painted. Holding tanks have been installed and panels for the hardtop are also completed. Our woodshop is working on the port forward bunk and the port aft cabin double bed option. Most of the cabinets have been pre-fitted and removed for varnish work.

We’re planning to start with engine installation this week. We’re also expecting to work on the hull windows around the 20th of June.