Production Update – Detailing

Your boat is coming close to her finishing line with the following progress being made:

Exterior: final finishing up on the deck fitouts with steering wheels, helm stations and helm seats installed, hardtop supports in place, and the cockpit table will soon be fitted. The granola cockpit flooring is going to be installed in the next few weeks.

Interior: all the cabins have been more than 80% completed. The outstanding works include fitting the roof panels, window liners, companion way steps, wardrobe, and little details like shelves, doors and locksets, hand rails, shower screen etc.

The saloon galley has been made a huge progress with all galley cabinets, Staron bench top, navigation station, and TV cabinets installed. The fitting of faucets, taps and the window blinds will soon start.

Engineering: the steering system is 90% completed with rudders and rudder cases are to be fitted. The electrical team is working hard to get the electrical wiring done in all cabins. The battery/inverter set up is finished. Navigation desk, TV entertainment system and air-conditioning electricals are 75% done.