Progress Update – Assembly Stage 2

INTERIOR

Port water tank installation is 100% done.

Windows liner on both sides are 50% done

Fiberglass windows panels are 100% done

Thru bulkhead access for heater and aircon is 80% done

Next week we will prepare head liner blocks, make provision for wiring harness and under bunk panels.

EXTERIOR

Cockpit gelcoat detailing in cockpit is 70% complete

Hull windows preparation is 100% done

Saloon windows preparation step is done, ready for installing windows.

Deck hatches dry-fitted – 50% complete