Production Update – Fit out

We are excited to inform you that your boat has been moved to the Fit out stage.

We have recently completed the installation of the windows, deck hatches, forward beam, A-frame, and engines. Our Production team is currently working on deck hardware (70%), plumbing (50%), steering (50%), electric (25%), and timber fitout (25%).