Your boat is progressing well in the last phase of Assembly stage.
We recently completed the installation of engines, deck hatches, forward beam, A-frame, stanchions, jib track & traveller, main sheet traveller track, winches, and deck organizer.
Our Production team is currently working on window installation, electric (15%), plumbing (20%), steering system (50%), and deck hardware (70%).