Production Update – Fitout

Your boat has been progressing well in the Fit-out stage and was recently equipped with some critical components.

At this stage, our Team has completed the installation of the ceiling panel frames, as well as the fuel and seawater systems. In addition, the window installation has also been completed.

We are currently working on interior gelcoat repairs (70% complete), the electrical system (45% complete), timberwork installation (25% complete), the grey water system (95% complete), and the freshwater system (90% complete). Installation of the bilge system, black water system, and Webasto heating system is also underway.

Production Update – Fitout

Your boat has moved to the next stage of production – Fitout.

The boat has recently been fitted with several components, marking significant progress in the build process. At this stage, our team has completed several critical components, including the BHD liner (carpentry), ceiling panel frames, fuel system, and bilge system.

We are now working on the electrical system (10% complete), bilge system, black water system, and window installation (90% complete).

Production Update – Assembly

Your boat is making progress in one of the first stages of production – Assembly.

At this point, the wall liner installation and the ceiling panel frames have been completed. Our team has also installed the glass on board.

Currently, we’re working on exterior gelcoat repairs, interior gelcoat repairs, and the electrical system (5% complete).