Hull is planned to bring over to our Seawind shed on 16th Oct after Lamination work is completed. Deck is ready and currently sitting in front of main office waiting to be moved to our Seawind shed for the joining to begin.

















Hull is planned to bring over to our Seawind shed on 16th Oct after Lamination work is completed. Deck is ready and currently sitting in front of main office waiting to be moved to our Seawind shed for the joining to begin.

















Tremendous progress has been achieved in the past month.
Interior: all tanks installation has been completed. Kitchen is almost done with all shelves, bench top, utilities installed. Electrical panel and Navigation desk are 100% done. Bed bases are completed including interior furniture. We are working on final detailing of bathrooms and running of electrical wiring.
Exterior: we have made quite a progress with the completion of starboard hull detailing, cockpit detailing, through holes and life raft access.



















Engineering: watermaker supports, holding tanks, water tanks, fuel tanks, pre-fit stanchions, and galley kick are now completed.