Your boat is progressing well in the Fit out stage.
We recently completed the installation of A-frame, stanchion, forward beam, windows and hatches.
Our Production team is currently working on trampoline, deck hardware (80%), electric work (70%), plumbing & LPG (70%), steering (50%), and timber fitout (50%).